Agency console
Run the agency side of an onboarding project
Move a project from draft to handover, work submissions and approvals, and use staffing and automation without bypassing evidence.
Who it’s for Platform owners and admins; group managers work only eligible projects in their own clinics
On this page
Activate the plan and deal with work that is blocked
- Open Onboarding → Projects → New project, choose the clinic and published template version, then set the platform lead, clinic owner and target date. Open the draft Plan to check shared steps, dates and dependencies.
- Activate the draft when ready. This makes its shared steps available and captures the baseline. In Settings, compare baseline and current dates; set a new baseline only after checking what will change. The Plan filters by owner, open, overdue and applicability. Use the list, board or timeline to find work held by a dependency. Add step creates project-specific work.
- Open a step to update assignee, watchers, due date, dependencies or details as permitted. Check Before and after before moving a date. Use Change selected to preview reassignment, a date shift or visibility change before applying. A date preview shows linked dates that would move; it does not change the baseline. Separate a shared comment from Platform only; edit or remove your own comment where offered.
- Start a step, record what it is Waiting on or resume it when the blocker clears. Ordinary tasks can be finished by a person; forms, files, approvals, training, voice facts and integration checks need their own evidence. Integration checks let you record the required stage and eligible test evidence, not declare an unperformed test run.
- Use a reason for reopen, waiver and marking a step not applicable where offered. Approval and voice fact steps cannot be waived like an ordinary task. Reopening a prerequisite can flag an already-completed dependent rather than automatically erasing that evidence. If someone else changed a record, reload before trying again.
- Put an active project On hold with a reason to stop its rules and nudges; resume to continue. Complete only when required applicable steps are settled and required approvals are no longer pending. An eligible completed project can be reopened with a reason; a canceled project cannot be resumed. Archive keeps completed or canceled work read-only. Completion never activates a phone line.
Change the clinic’s onboarding page
- Open the project’s Settings → Clinic portal. This is a clinic-level setting: a save changes the portal for all of that clinic’s onboarding projects. A platform admin or an eligible manager of the clinic’s group can edit it.
- Under Welcome text, choose Write for up to 4,000 characters, then Preview to see how the clinic will read it. A blank welcome starts the page with its next steps instead. Use simple headings, bold, lists or secure links without patient information.
- In Contacts choose Add a contact or Remove. Add up to ten contacts in the order the clinic should see them. Name and role are required (up to 120 and 60 characters); email and phone are optional.
- In Sections, use Show for each item and the Move up or Move down controls to set its order. Use the platform’s default order restores only the order and keeps the current show/hide choices. Voice setup appears only for a clinic with voice service, even if its Show switch is on.
- Select Save clinic portal and reopen the clinic portal to verify. If someone saved first, the stale save is refused and the latest version reloads. Compare it and re-enter only the intended changes. Fix any marked field errors before trying again.
Review the clinic’s submitted answers before using them
- Use My onboarding work or Waiting for review to find work, then open the project’s Information tab and the form. Distinguish a saved draft from a submitted revision. Review the revision the clinic actually sent.
- Choose Accept answers if correct, or Request changes with a specific note. If the clinic later submits a new revision, review opens again and approvals tied to the prior revision may be superseded.
- Accepted is not applied. In Apply to the clinic’s settings, choose the mapped groups, preview Now and From the form, and inspect what will be written or skipped. Use Apply changes only after checking the preview. If the selection or settings changed, preview again; a stale preview writes nothing. Read the apply results and history and check the resulting clinic settings.
Review a clean upload, lock documents and decide approvals
- In Documents → Requested documents, use Ask for a document when there is a document step and specify the slot requirements. Wait for a clean scan before opening the upload or accepting or rejecting it. A rejected file needs a replacement; a file refused by scanning cannot be downloaded. The step completes only when all required slots have accepted clean evidence. Do not upload patient information.
- To create a project document, choose New document and its kind and audience. Preview before saving and use History to compare revisions. Editing a document can supersede approvals on the old revision. Lock only a final document: nobody, including the agency, can edit it after locking.
- In Approvals, choose Request approval and set the subject, completing step if any, named approvers, due date and whether any one, everyone or an ordered sequence must approve. Only the right approvers can decide; clinic-side approvers are clinic admins. If the platform records for a clinic approver, enter the audited reason the clinic can read.
- Approve, Reject or Ask for changes on the current revision. Cancel an eligible pending approval if no longer needed. If the subject changes or the approval is Superseded, review the new revision and request a new approval; an old approval cannot complete the new evidence.
Assign training and choose the audience for updates
- Open Training → Assign training. Choose the training step, a published resource and eligible people. Use Verify or waive only after checking who was assigned. Record Verified: they can do it or Not needed for this person; give the reason for a waiver. A later version can require a new acknowledgement.
- In Updates use New update and start blank or from an offered project summary. Draft, edit and preview. Choose The clinic (shared) or Platform only before Publish. Published updates are final; a platform-only update never appears to the clinic. Use the project’s Activity to check who changed material and when.
Try a rule and investigate a missed nudge
- Open Onboarding → Automation → Rules and nudges and choose a project. Add a project rule with one trigger, conditions that must all hold and up to ten actions. Use only answers that were made available to rules. A project’s rule acts on that project; it does not trigger itself.
- Use the rule menu’s Try it, choose As if and the underlying step where applicable, and run the preview. Review why it would not run or what actions would follow. No steps change and no one is notified. Change, Pause, Turn on and Remove affect a project’s own rules; inherited rules must be changed in the template.
- Under Nudges, set when reminders start and repeat, the maximum per step and when to tell the project lead. Zero maximum sends none. The daily email-summary option does not override quiet hours, preferences or the platform’s email switch. Saving a rule or seeing a preview does not establish delivery.
- In Automation, compare Rule runs and Deliveries and narrow by clinic and result. Queued waits for its delivery window; Sent is distinct from Suppressed or Failed. Check current membership, the settled step, a moved due date, delivery preference, quiet hours or a cap before escalating a miss. Repeated failures are surfaced after retries. Onboarding email is gated separately and contains a fixed notice with a sign-in link, not a step, file or comment.
Plan staffing and interpret portfolio figures
- Use Programs → New program to group projects. From the program, add eligible projects, remove a project, rename or archive the program. A project already in a program is not offered for another. Archiving a program is not canceling its projects.
- Open Workload and choose weeks. Compare assigned steps with estimated hours by person; waiting on the clinic is not work effort. Use Away weeks for a person to record unavailability. Check assignments before acting on load; an estimate is not time tracked.
- Open Reports and filter dates, Kind, Program and Project lead. Read How these are counted, then use Show its projects where offered. Some metrics drill down only for dates ending today. The open/overdue trend needs at least two snapshots; earlier days can count shared steps only.
- Use Notifications and Preferences for personal delivery choices. For an activated project, Overview → Project report gives its counts; an eligible Export project requests a recent sign-in and a reason and returns a short-lived JSON download. A never-activated draft has no export. For a moved clinic’s eligible old records, Former-clinic archive is separately read-only and may show downloads only where allowed; it does not reopen the new agency’s clinic or projects.